6) Design towards Intermediate Review

Re-order proposal conceptual into design conceptual based on workflow

Extract all Racked Equipment from the equipment list and initially place
in racks/consoles based on Conceptual, workflow and equipment list headings

Generate Patching Elevations

Determine power and heat loading

Determine any path choke points and single points of failure

Confirm router sizes and patch panel throughput

Confirm server and other storage suitability as quoted

Determine DA usage

Determine system timing based on conceptual/workflow requirements

Determine all equipment that requires reference and generate initial reference drawings

Generate initial Network Drawings

Generate Test Plan

Generate Implementation and cut over plan

Finalize equipment placement in racks and consoles

Finalize power and heat loading

Intermediate Design review

Implement changes from design review

Start Equipment Procurement